Current Projects Updates
CURRENT PROJECT UPDATES
H2 Construction:
Restoration Tentative Production Schedule
February 20th 2026
Issued Building Permits:
January 9th 2026
January 7th 2026
Issued Window & Slider Door Permits Columbia
Issued Window & Slider Door Permits Enterprise
December 4th 2025
November 13th 2025
Elias Brother will be on property setting up and assessing restoration plan.
Consult Engineers will be on Lanais to resume testing.
October 28, 2025
Restoration Project for the Structural Integrity & Wind Repairs.
Restoration Project Update Communication
Restoration Project Update Communication
September 19, 2025
Restoration Project for the Structural Integrity & Wind Repairs.
March 18th, 2025
STOP WORK ORDER
TO ALL OWNERS,
Afternoon All, as you’re probably aware, we received a STOP WORK ORDER that was placed on the project at SB by the County. Note that the County Inspector notified us that the County received a call from the EPA who received an anonymous report about work being completed without a permit. As we know Florida Structural was instructed by our engineers to begin demo, and it is common practice to begin demo work while the permits are in review, as long as nothing is covered up so the inspectors can inspect. Note that the inspector said doing demo while waiting for the permit is not unusual, but because of the complaint, the Stop Work Order had to be placed. Also note, there will NOT be a fine assessed for this action.
Thank you, Schooner Bay Board of Directors
TO ALL OWNERS,
Afternoon All, as you’re probably aware, we received a STOP WORK ORDER that was placed on the project at SB by the County. Note that the County Inspector notified us that the County received a call from the EPA who received an anonymous report about work being completed without a permit. As we know Florida Structural was instructed by our engineers to begin demo, and it is common practice to begin demo work while the permits are in review, as long as nothing is covered up so the inspectors can inspect. Note that the inspector said doing demo while waiting for the permit is not unusual, but because of the complaint, the Stop Work Order had to be placed. Also note, there will NOT be a fine assessed for this action.
Thank you, Schooner Bay Board of Directors
Asbestos & Lead Based Paint Testing Results
SBA Loan:
The SBA Loan was approved by the Schooner Bay owners at a membership meeting with a vote of 129 yes votes; 3 no votes.
SBA requires posting of the organization practices enclosed below.
2022 Lanai Inspection Report: